Progress billing: how to invoice a large job in stages

How progress billing works for contractors: setting a payment schedule, what each progress invoice shows, and how holdbacks and retainage work.

An open-plan kitchen and living space mid-renovation, with bare walls, tools and materials on the floor.

The short answer

Progress billing means invoicing a large job in agreed stages instead of all at the end. Agree the schedule in the estimate, tie each payment to a milestone the client can see (or to a percentage of work complete), and send a progress invoice when each stage is reached. Each invoice should show the full contract value, approved changes, work completed to date, what was billed before, any holdback or retainage, and the amount now due.

On a small job you invoice when you finish. On a job that runs for six weeks, that means paying for six weeks of labour, materials and subcontractors before you see a dollar. One slow-paying client can sink a small business that way, even when the work itself is profitable.

Progress billing fixes the cash flow. You agree up front to invoice in stages, and each payment covers the work done so far.

When should you use progress billing?

  • Jobs that last more than two or three weeks.
  • Jobs where materials or subcontractors cost a large share of the price.
  • Commercial work, where the client expects regular payment applications.
  • Any job big enough that a late final payment would hurt your business.

Milestones or percentage complete?

There are two common ways to decide what each invoice covers. Milestone billing ties each payment to a stage both of you can see. Percentage-of-completion billing charges for the share of each part of the job finished since the last invoice, which is common on larger commercial projects.

Milestone billing vs percentage-of-completion billing
MethodHow it worksBest for
MilestonesA fixed amount when each agreed stage is reachedRenovations and residential work
Percentage completeBills the share of each line finished since the last invoiceLarger commercial projects
Time-basedAn invoice every two weeks or month for work doneLong jobs with steady progress

For most small contractors, milestones are simpler. The client can see the stage is done, so there is little to argue about.

How do you set the billing schedule in the estimate?

The payment schedule belongs in the estimate or contract the client approves, not in the first invoice. A typical schedule for a $40,000 bathroom and kitchen renovation might look like this:

Example progress payment schedule on a $40,000 job
StageShareAmount
Deposit on signing10%$4,000
Demolition complete and materials delivered25%$10,000
Rough-in plumbing and electrical passed25%$10,000
Drywall, tile and cabinets installed25%$10,000
Final walkthrough complete15%$6,000

What should each progress invoice show?

A progress invoice should let the client see the whole picture, not just this month’s number:

  1. The original contract value, plus approved change orders, as the current contract total.
  2. Which stage this invoice is for, or the percentage of each part now complete.
  3. The total value of work completed to date.
  4. Less: everything already invoiced.
  5. Less: any holdback or retainage, if it applies.
  6. Tax, and the amount now due, with a due date.
Example: third progress invoice
LineAmount
Contract total including change orders$41,250.00
Work completed to date (stages 1–3)$24,000.00
Less previously invoiced−$14,000.00
This invoice: rough-in complete$10,000.00
Balance remaining on contract after this invoice$17,250.00

What are holdbacks and retainage?

On construction work, clients often keep back a percentage of each payment until the job is finished. The rules depend on where you work:

  • Canada: most provinces require a holdback on construction contracts, commonly 10 percent, released after the job is complete and the lien period has passed. Ontario’s Construction Act also sets prompt payment deadlines for proper invoices.
  • United States: retainage is usually set by the contract, often 5 to 10 percent, and some states cap it or set when it must be released.
  • Australia: retention is set by the contract, often around 5 percent, and each state and territory has security of payment legislation that gives a right to progress payments and sets timelines for payment claims.

Show any holdback as its own line on every progress invoice, and keep a running total of how much is being held. When the job is complete, invoice for its release separately. This is general information, not legal advice; lien, holdback and payment claim rules are strict, so check what applies to your work.

How do you keep progress billing moving?

  • Invoice the day a stage is reached, not at the end of the month.
  • Take a photo of each completed stage and attach it to the invoice.
  • Do not start the next stage while the previous invoice is seriously overdue.
  • Add change orders to the contract total as soon as they are approved, so every invoice is up to date.

Common questions

What is progress billing?

Progress billing is invoicing a project in stages as the work is completed, rather than once at the end. Each progress invoice bills for the work done since the last one, based on milestones or a percentage of completion agreed at the start.

How do I set up a progress payment schedule?

Agree it in the estimate or contract before work starts. Tie each payment to a milestone the client can see, such as materials delivered, rough-in complete or final walkthrough, and give each stage an amount or percentage of the contract and a due date after invoicing.

What is a holdback or retainage?

A holdback (Canada) or retainage or retention (US and Australia) is a percentage of each progress payment the client keeps back until the job is finished, as security for completion and defects. In most Canadian provinces it is a legal requirement on construction work, commonly 10 percent; in the US and Australia it is usually set by the contract.